TVA: Watts Bar More Than 90 Percent Complete

AP

Print | Front Page | Email this story | Comments ()

SPRING CITY, Tenn. (AP) – The Tennessee Valley Authority says work on the Watts Bar Nuclear Plant is more than 90 percent complete.

The federal agency announced a target completion date for the plant's Unit 2 reactor of December 2015.

It said this week that the reactor continues to meet safety and quality targets and remains on schedule and within budget.

The facility is on course to become the nation's first new nuclear generating plant of the 21st century.

About 3,200 workers are on the Watts Bar 2 project, which will be TVA's seventh nuclear unit. Watts Bar 2 will add 1,100 megawatts of electricity, providing enough energy for approximately 650,000 homes.

TVA is the nation's largest public utility, supplying power to about 9 million people in Tennessee, Alabama, Mississippi, Kentucky, Georgia, North Carolina and Virginia.

Copyright 2014 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Sign-Up For Our Free Email Edition
Get the news first with our daily email


 
Blog News, Training & Events
RECORD TOTALS DAY WEEK YEAR
PROPERTY SALES 92 374 12,495
MORTGAGES 109 432 14,525
FORECLOSURE NOTICES 0 0 0
BUILDING PERMITS 160 680 26,098
BANKRUPTCIES 53 218 8,378
BUSINESS LICENSES 24 99 4,212
UTILITY CONNECTIONS 40 230 9,191
MARRIAGE LICENSES 11 49 3,055

Weekly Edition

Issues | About

The Memphis News: Business, politics, and the public interest.